June 2010 - September, 2010
- Early design work and schematic design
- Sale of bonds
October 2010 - May, 2011
- Design development
- Construction document
- Bidding
- Award of bid
June 2011 - July 2012
- Renovation of 500-600-700 halls
- Installation of mechanical systems in basement area currently occupied by band and music programs
- New construction on 100/200 hall classroom wing, auxiliary gym/locker room, and music suite
July 2012 - August 2013
- Demolition of old 100/200 classroom wing and gym
- New construction of media center, multipurpose room, and main office
- Renovation of pool, south gym, dining hall, auditorium and library
- Athletic field renovations and improvements
|
|